OPENING CEREMONY (04.11.2021)
SHANTHI POOJA (03.11.2021)
FINISHING WORKS (17.06.2021)
PANTRY CUPBOARD FINISHING WORKS (27.03.2021)
LAYING THE MEMBRANE SHEET ON ROOF TOP (WATERPROOFING) & FIXING OF WATER METERS (22.03.2021)
EXTERNAL PAINTING WORKS (03.03.2021)
FIXING OF DOORS & DOOR FRAMES (15.01.2021)
FIXING OF PANTRY CUPBOARDS (24.12.2020)
BATHROOM TILING WORK (11.11.2020)
5th FLOOR BED LEVELING WORK (22.09.2020)
OUT SIDE WALL PLASTERING WORKS & BATHROOM FLOOR CHIPPING WORKS (20.08.2020)
SWIMMING POOL SLAB, GYM ROOM ROOF CONCRETE WORKS (28.07.2020)
FIXING OF DOOR FRAMES & SWIMMING POOL SLAB REINFORCEMENT WORK (21.07.2020)
INSTALLATION OF WALL MOUNTED – WATER CLOSET CISTERN (07.07.2020)
FORM WORK FOR MACHINE ROOM & OVER HEAD WATER TANK (25.06.2020)
ROOF TOP RETAINING WALL CONCRETE WORKS & 6TH FLOOR UNIT PARTITION WORK (10.06.2020)
SWIMMING POOL COLUMN CONCRETE WORKS ON ROOFTOP (15.05.2020)
ROOFTOP SLAB CONCRETE & 3rd FLOOR ELECTRICAL WORKS (15.03.2020)
ROOF SLAB REINFORCEMENT WORK (15.02.2020)
APPLYING SKIM COAT TO THE WALLS (30.01.2020)
6th FLOOR SLAB CONCRETE & 3rd FLOOR UNIT PARTITION WORKS (15.01.2020)
3rd FLOOR UNIT PARTITION WORKS (30.12.2019)
1ST FLOOR UNIT PARTITION WORKS (30.11.2019)
SITE POOJA ST 29 (11.11.2019)