OPENING CEREMONY (18.02.2018)
–FINISHING WORKS (01.02.2018)
–FINISHING WORKS (28.12.2017)
– FIXING OF PANTRY CUPBOARD & PAINTING WORKS (16.11.2017)
– INTERNAL TILING & PAINTING WORKS (31.10.2017)
– INTERNAL TILING & PAINTING WORKS (15.10.2017)
– INTERNAL TILING WORKS (02.10.2017)
– INTERNAL TILING WORKS (14.09.2017)
– INTERNAL TILING WORKS (01.09.2017)
WINDOW FRAME FIXING & BATHROOM TILING WORKS (15.08.2017)
PAINTING & TILING WORKS (30.07.2017)
6TH FLOOR BED LEVELING WORK (15.07.2017)
TILE BED LEVELING WORKS (01.07.2017)
APPLYING SKIN CODE AND DOOR FRAME WORKS (16.06.2017)
1ST CODE WALL PAINTING WORKS (01.06.2017)
COMPLETING THE STRUCTURAL WORKS (15.05.2017)
6th FLOOR UNIT PARTITION WORKS (30.04.2017)
6th FLOOR UNIT PARTITION WORKS (15.04.2017)
SHUTTERING WORKS FOR ROOF TOP & 6TH FLOOR UNIT PARTITION (01.04.2017)
SHUTTERING WORKS FOR 8th FLOOR SLAB & 4th FLOOR UNIT PARTITION (15.03.2017)
REINFORCEMENT WORKS FOR 8th FLOOR COLUMN & 3rd FLOOR UNIT PARTITION (01.03.2017)
FORM WORKS FOR 7th FLOOR SLAB & 2nd FLOOR UNIT PARTITION WORKS (15.02.2017)
SHUTTERING WORKS FOR 6TH FLOOR SLAB & 1ST FLOOR UNIT PARTITION WORKS (31.01.2017)
REINFORCEMENT WORKS FOR 6TH FLOOR COLUMN (6.01.2017)
FORM WORKS FOR 5TH FLOOR SLAB (01.01.2017)
SHUTTERING WORKS FOR 4TH FLOOR SLAB (16.12.2016)
CONCRETE WORKS 3RD FLOOR SLAB (30.11.2016)
FORM WORKS FOR 3RD FLOOR SLAB (17.11.2016)
REINFORCEMENT WORKS FOR 2ND FLOOR SLAB (31.10.2016)
COLUMN WORKS FOR 2ND FLOOR SLAB (19.10.2016)
BEAM REINFORCEMENT WORKS FOR 1ST FLOOR (30.09.2016)
FORM WORKS FOR 1ST FLOOR SLAB (15.09.2016)
REINFORCEMENT WORKS OF GROUND FLOOR (31.08.2016)
PROVISIONS FOR SHUTTERING WORKS OF GROUND FLOOR (16.08.2016)
COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR (30.07.2016)
BASEMENT CONCRETE WORKS (16.07.2016)
REINFORCEMENTS WORKS FOR RAFTS BEAM – FINAL STAGE (30.06.2016)
REINFORCEMENTS WORKS FOR RAFTS BEAM (15.06.2016)
SCREED CONCRETE WORKS (31.05.2016)
RAFT BEAM WORKS (15.05.2016)
COMPLETION OF EXCAVATION WORKS (30.04.2016)
COMPLETION OF EXCAVATION WORKS (18.04.2016)
SHORING WORKS & EXCAVATION WORKS (17.03.2016)
SHORING WORKS & EXCAVATION WORKS (02.03.2016)
SHORING WORKS (16.02.2016)
STONE LAYING CEREMONY (27.01.2016)
BHOOMI POOJAI (26.01.2016)
SOIL TESTING (21.01.2016)
DEMOLISHING WORKS (11.01.2016)
PUNNIYASTHANA POOJA (06.01.2016)