OPENING CEREMONY (26.07.2018)
FINISHING WORKS (28.12.2017)
FINISHING WORKS (28.11.2017))
FIXING OF BATHROOM ACCESSORIES & PAINT WORKS (31.10.2017))
INTERNAL TILING & DOOR WORKS (15.10.2017)
INTERNAL TILING WORKS (02.10.2017)
INTERNAL TILING WORKS (15.09.2017)
INTERNAL TILING WORKS (01.09.2017)
TILING WORKS FOR BATHROOMS (15.08.2017)
TILING WORKS FOR BATHROOMS (30.07.2017)
4TH FLOOR BED LEVELING WORKS & BATHROOM PLUMBING WORKS (15.07.2017)
7TH FLOOR DOOR FRAME FIXING WORKS (01.07.2017)
5TH FLOOR DOOR FRAME FIXING WORKS (16.06.2017)
DOOR FRAME FIXING & 1ST CODE WALL PAINTING WORKS (01.06.2017)
REINFORCEMENT WORK FOR ROOF TOP(15.05.2017)
SHUTTERING WORKS FOR ROOF TOP SLAB & 9th FLOOR UNIT PARTITION WORK (30.04.2017)
SHUTTERING WORKS FOR ROOF TOP COLUMN & 8th FLOOR UNIT PARTITION WORK (15.04.2017)
REINFORCEMENT WORKS FOR 12th FLOOR SLAB (01.04.2017)
REINFORCEMENT WORKS FOR 11th FLOOR SLAB & 6th FLOOR UNIT PARTITION (15.03.2017)
REINFORCEMENT WORKS FOR 11th FLOOR COLUMN & 5th FLOOR UNIT PARTITION (01.03.2017)
SHUTTERING & CONCRETE WORKS FOR 10th FLOOR COLUMN & 4th FLOOR UNIT PARTITION (15.02.2017)
CONCRETE WORKS FOR 9TH FLOOR COLUMN (31.01.2017)
REINFORCEMENT WORKS FOR 9th FLOOR COLUMN (16.01.2017)
REINFORCEMENT WORKS FOR 8th FLOOR SLAB (01.01.2017)
REINFORCEMENT WORKS FOR 7TH FLOOR SLAB (16.12.2016)
COLUMNS WORKS FOR 7TH FLOOR SLAB (30.11.2016)
REINFORCEMENT WORKS FOR 6TH FLOOR SLAB & 1ST FLOOR UNIT PARTITIONS (17.11.2016)
COLUMN CONCRETE WORKS FOR 6TH FLOOR SLAB (31.10.2016)
REINFORCEMENT WORKS FOR 5th FLOOR SLAB (19.10.2016)
COMPLETED CONCRETE WORKS FOR 4th FLOOR SLAB (30.09.2016)
FORM WORKS FOR 4th FLOOR SLAB (15.09.2016)
REINFORCEMENT WORKS FOR 3rd FLOOR SLAB – 1ST STAGE (31.08.2016)
CONCRETE WORKS FOR 3rd FLOOR COLUMN (16.08.2016)
CONCRETE WORKS FOR 2nd FLOOR SLAB (05.08.2016)
REINFORCEMENT WORKS FOR 2nd FLOOR SLAB – final Stage (30.07.2016)
REINFORCEMENT WORKS FOR 2nd FLOOR SLAB – 3rd Stage (16.07.2016)
REINFORCEMENT WORKS FOR 2nd FLOOR SLAB – 2nd Stage (30.06.2016)
SHUTTERING WORKS FOR 2nd FLOOR SLAB – 2nd Stage (15.06.2016)
SHUTTERING WORKS FOR 2nd FLOOR SLAB (31.05.2016)
REINFORCEMENT AND SHUTTERING WORKS FOR 2nd FLOOR COLUMN WORKS (16.05.2016)
SHUTTERING WORK FOR 1ST FLOOR (30.04.2016)
COLUMN REINFORCEMENT WORK FOR 1ST FLOOR (20.04.2016)
GROUND FLOOR CONCRETE WORKS (17.03.2016)
GROUND FLOOR REINFORCEMENT WORKS (05.03.2016)
GROUND FLOOR SLAB SHUTTERING WORKS (30.01.2016)
GROUND FLOOR COLUMN CONCRETE WORKS (16.01.2016)
BASEMENT SLAB CONCRETING (31.12.2015)
SHUTTERING WORKS FOR GROUND FLOOR COLUMN (30.11.2015)
BASEMENT SLAB REINFORCEMENT WORKS (31.10.2015)
BASEMENT REINFORCEMENT WORKS (17.09.2015)
PILING WORKS (05.08.2015 – 17.09.2015)
PILE CAP REINFORCEMENTS (13.07.2015)
EXCAVATION PROGRESS (19.05.2015)
PILING CONCRETE (17.12.2014)
STONE LAYING CEREMONY (12.09.2014)
BHOOMI POOJAI (11.09.2014)
SOIL TESTING (29.07.2014)