OPENING CEREMONY  –  (05.04.2023)

SHANTHI POOJA  –  (04.04.2023)

COMPLETED APARTMENTS  –  (20.03.2023)

FINISHING WORKS –  (17.02.2023)

INTERNAL FINISHING WORKS –  (19.11.2022)

EXTERNAL & INTERNAL FINISHING WORKS –  (22.10.2022)

 

INSTALLATION OF THE ELEVATOR (LIFT), WATER METERS AND FIRE & SAFETY SYSTEM –  (16.09.2022)

EXTERNAL FINISHING WORKS –  (25.08.2022)

EXTERNAL PAINTING WORKS –  (21.07.2022)

FIXING OF PANTRY CUPBOARD BASE FRAMES –  (11.06.2022)

LAYING THE MEMBRANE SHEET ON ROOF TOP (WATERPROOFING – (12.05.2022)

2nd FLOOR BATHROOM TILING WORKS – (26.04.2022)

FIXING OF ALUMINIUM DOORS & WINDOWS –  (05.03.2022)

ROOF TOP RETAINING WALL CONCRETE WORK –  (07.01.2022)

ROOF TOP SLAB CONCRETE WORK – ENTIRE STRUCTURAL WORK IS COMPLETED (05.12.2021)

ROOF TOP FORM WORK, 7th FLOOR UNIT PARTITION WORK & APPLYING THE WALL PUTTY TO 3rd FLOOR WALLS (27.11.2021)

ROOF TOP – COLUMN CONCRETE WORK (27.10.2021)

8th FLOOR SLAB CONCRETE WORK (14.10.2021)

FORM WORK FOR 8th FLOOR SLAB & INSTALLATION OF 2nd FLOOR DOOR FRAMES (21.09.2021)

APPLYING THE SKIM COAT TO 2nd  FLOOR INTERNAL WALLS &  EXTERNAL  WALL  PLASTERING  WORKS (28.08.2021)

7th FLOOR SLAB CONCRETE WORK (20.08.2021)

6th FLOOR SLAB CONCRETE WORK (14.07.2021)

6th FLOOR SLAB REINFORCEMENT WORK (12.07.2021)

6th FLOOR COLUMN CONCRETE & 2nd FLOOR – UNIT PLASTERING WORK (21.06.2021)

2nd FLOOR – UNIT PARTITION WORK (11.06.2021)

5th FLOOR SLAB – CONCRETE WORK (03.06.2021)

5th FLOOR – FORM  WORK & 1ST FLOOR – UNIT PARTITION WORK (11.05.2021)

4th FLOOR SLAB – CONCRETE WORK (08.04.2021)

4th FLOOR SLAB – FORM WORK (30.03.2021)

3rd FLOOR SLAB – CONCRETE WORK (11.03.2021)

3rd FLOOR SLAB – REINFORCEMENT WORK (03.03.2021)

3rd FLOOR SLAB – COLUMN CONCRETE WORK (12.02.2021)

2nd FLOOR SLAB – CONCRETE WORK (29.01.2021)

2nd FLOOR SLAB – REINFORCEMENT WORK (15.01.2021)

2nd FLOOR SLAB – COLUMN CONCRETE WORK (15.12.2020)

2nd FLOOR SLAB – COLUMN REINFORCEMENT WORK (30.11.2020)

1st FLOOR SLAB CONCRETE WORK (19.11.2020)

1st FLOOR SLAB REINFORCEMENT WORK (09.11.2020)

1st FLOOR SLAB – BEAM REINFORCEMENT WORK (14.10.2020)

1st FLOOR COLUMN CONCRETE WORK (18.09.2020)

GROUND FLOOR SLAB CONCRETE WORK (04.09.2020)

GROUND FLOOR SLAB REINFORCEMENT WORK (27.08.2020)

GROUND FLOOR SLAB FORM WORK (15.08.2020)

GROUND FLOOR SLAB FRONT SIDE & RETAINING WALL CONCRETE WORKS (29.07.2020)

BASEMENT STAIRCASE, RAMP & GROUND FLOOR COLUMN, POST – CONCRETE WORKS (18.07.2020)

GROUND FLOOR COLUMN CONCRETE WORKS (01.07.2020)

BASEMENT RETAINING WALL FORM WORK & GROUND FLOOR COLUMN REINFORCEMENT WORK (23.06.2020)

BASEMENT POST CONCRETE SETTING OUT WORK (10.06.2020)

BASEMENT CONCRETE WORK (02.06.2020)

BASEMENT REINFORCEMENT WORK FINAL STAGE (15.05.2020)

SCREED CONCRETE & BASEMENT REINFORCEMENT WORKS (15.02.2020)

EXCAVATION WORKS (30.01.2020)

EXCAVATION WORKS (15.01.2020)

SHORING WORKS (30.12.2019)

SHORING WORKS (30.11.2019)

FOUNDATION STONE LAYING CEREMONY (24.10.2019)

BHOOMI POOJA (23.10.2019)

DEMOLISHING WORKS (19.10.2019)

PUNNIYASHTHANA POOJA (11.10.2019)

SOIL TESTING (20.11.2019)

LAND OF THE PROPOSED PROJECT ST 27 (11.10.2019)

 