Completed Project Gallery >Span Tower 19

OPENING CEREMONY (21.09.2019)

FINISHING WORKS (15.05.2019)

INSTALLATION OF TIMBER FLOORING (01.05.2019)

FIXING OF WINDOW FRAMES, PANTRY CUPBOARDS & GRANITE TOPS (01.04.2019)

FIXING OF WINDOW FRAMES & PANTRY CUPBOARDS (15.03.2019)

EXTERNAL PAINTING WORKS & DOOR FIXING WORKS (01.03.2019)

PROVISION FOR INSTALLING THE LIFT & OTHER FINISHING WORKS
(15.02.2019)

BATHROOM TILING WORK (01.02.2019)

FIXING OF DOOR FRAMES (15.01.2019)

BATHROOM TILING WORK (01.01.2019)

APPLYING PUTTY TO THE INTERNAL WALLS (01.11.2018)

STARTING THE 1ST FLOOR CHIPPING WORK (01.10.2018)

COMPLETED THE STRUCTURAL WORKS (01.09.2018)

REINFORCEMENT WORK FOR ROOF TOP SLAB & 6TH FLOOR 1ST CODE PAINTING WORKS (15.08.2018)

CONCRETE WORKS FOR ROOF TOP COLUMN & 5TH FLOOR 1ST CODE PAINTING WORKS (01.08.2018)

CONCRETE WORKS FOR 11TH FLOOR COLUMN & BASEMENT WATER PROOFING WORKS (15.07.2018)

REINFORCEMENT WORKS FOR 11TH FLOOR COLUMN (01.07.2018)

CONCRETE WORKS FOR 10TH FLOOR COLUMN & 7TH FLOOR UNIT PARTITION WORK (15.06.2018)

CONCRETE WORKS FOR 9TH FLOOR COLUMN & 6TH FLOOR UNIT PARTITION WORK (15.05.2018)

SHUTTERING WORKS FOR 8TH FLOOR SLAB & 4TH FLOOR UNIT PARTITION WORK (01.05.2018)

REINFORCEMENT WORKS FOR 8TH FLOOR COLUMN & 3RD FLOOR UNIT PARTITION WORK (01.04.2018)

FORM WORKS FOR 6TH FLOOR SLAB & 1ST FLOOR UNIT PARTITION WORK (01.03.2018)

REINFORCEMENT WORKS FOR 6TH FLOOR COLUMN (15.02.2018)

FORM WORKS FOR 5TH FLOOR SLAB (01.02.2018)

REINFORCEMENT WORKS FOR 4TH FLOOR SLAB (16.01.2018)

SHUTTERING WORKS FOR 4TH FLOOR COLUMN(28.12.2017)

2ND FLOOR SLAB REINFORCEMENT WORKS (16.11.2017)

2ND FLOOR COLUMN CONCRETE WORKS (31.10.2017)

1st FLOOR SLAB CONCRETE WORKS (15.10.2017)

1ST FLOOR SLAB TOP & BOTTOM REINFORCEMENT WORKS (02.10.2017)

REINFORCEMENT WORKS FOR 1ST FLOOR SLAB FINAL STAGE (15.09.2017)

REINFORCEMENT WORKS FOR 1ST FLOOR SLAB FINAL STAGE (31.08.2017)

REINFORCEMENT WORKS FOR 1ST FLOOR SLAB 2nd STAGE (15.08.2017)

REINFORCEMENT WORKS FOR 1ST FLOOR SLAB (30.07.2017)

SHUTTERING WORKS FOR 1ST FLOOR SLAB (15.07.2017)

1st floor column concrete works final stage (01.07.2017)

1st floor column concrete works (16.06.2017)

REINFORCEMENT WORKS FOR MEZZANINE FLOOR SLAB (01.06.2017)

 

FORM WORKS FOR 1ST FLOOR SLAB (15.05.2017)

CONCRETE WORKS FOR BASEMENT RAMP & 1st FLOOR COLUMN CONCRETE WORKS (30.04.2017)

 

CONCRETE WORKS FOR GROUND FLOOR SLAB (15.04.2017)

SHUTTERING & REINFORCEMENT WORKS FOR GROUND FLOOR SLAB (01.04.2017)

 

 

SHUTTERING WORKS FOR GROUND FLOOR COLUMN & SLAB (15.03.2017)

 

CONCRETE WORKS FOR BASEMENT SLAB (01.03.2017)

 

REINFORCEMENT WORKS FOR BASEMENT SLAB & SUMP (15.02.2017)

 

 

SCREED CONCRETE & BASEMENT SUMP PROVISION WORKS (31.01.2017)

SCREED CONCRETE & BASEMENT BEAM REINFORCEMENT (16.01.2017)

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB – 3rd STAGE (01.01.2017)

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB – 2ND STAGE (16.12.2016)

 

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB  (30.11.2016)

 

PILE CAP DEMOLISHING WORK – FINAL STAGE (17.11.2016)

 

 

PILE CAP DEMOLISHING WORK – 2ND STAGE (31.10.2016)

 

EXCAVATION WORKS & PILE CAP DEMOLISHING WORKS (19.10.2016)

SHORING WORKS (30.09.2016)

PILING WORKS  COMPLETED (15.09.2016)

 

PILING WORKS  – Final stage (31.08.2016)

 

PILING WORKS  – 2nd stage (16.08.2016)

PILING WORKS  – 1st stage (30.07.2016)

FOUNDATION STONE LAYING CEREMONY  (14.07.2016)

 

BHOOMI POOJA (13.07.2016)

 

PROJECT AREA (15.05.2016)

 

ALLOCATING THE PROJECT AREA (30.04.2016)

 

COMPLETION OF SOIL TESTING (18.04.2016)

 

SOIL TESTING (17.03.2016)

 

DEMOLISHING WORKS (16.02.2016)

 

PUNNIYASTHANA POOJAI (10.02.2016)